STORM LAKE, IA (Northwestiowanow) – Work on the Scout Park and Icehouse lift stations is nearing completion, with both new facilities now fully operational.
The new lift stations are located near Lighthouse Drive and the southwest end of Vista Drive. The infrastructure upgrades were designed to increase sanitary sewer capacity, help protect local waterways, and reduce the risk of service interruptions during flood events.
City officials say the temporary pumps used during construction have now been removed, and crews are finishing concrete and turf restoration work at the sites.
Residents are asked to avoid walking on newly installed sod to allow it to become established properly.
Contractors are expected to continue addressing warranty-related items as needed in the coming days. While the project areas are generally accessible, the city is encouraging the public to use caution and avoid active work areas when contractor crews are present.